The City of Prince George 2011 Capital Road Rehabilitation Program will continue next week.
Projects:
Where - Ospika Boulevard north bound lanes between 5th and 15th Avenues
When - Asphalt milling June 20 with paving on June 24 (Paving is weather dependant)
Duration - 1 week
Length - 2.32 lane kilometers
Estimated Cost - $312,820
Where - Ospika Boulevard south bound lanes between Massey Drive and Ferry Avenue
When - Asphalt milling June 21 with paving on June 27 (Paving is weather dependent)
Duration - 1 week
Length - 2.53 lane kilometers
Estimated Cost - $334,530
Where - Domano Boulevard between Moriarty and Trent
When - Asphalt milling June 22 with paving on June 28t(Paving is weather dependent)
Duration - 1 week
Length - 2.53 lane kilometers
Estimated Cost - $334,530
Where - P.G. Pulpmill Road between the east city limit and 685m west
When - Asphalt milling June 23 with paving on June 29 and 30 (Paving is weather dependent)
Duration - 1 week
Length - 1.37 lane kilometers
Estimated Cost - $389,170
"In 2011, council has committed to a road rehabilitation record budget of $3.5 million, up about 2.9 per cent from last year, with 11 capital paving projects identified for improvement," said Mayor Dan Rogers. "In addition to the capital program, there is also the road repair budget that includes approximately a million dollars for patching as part of the asphalt maintenance program."
Additionally, in 2012, council has committed to increase the annual road rehabilitation budget of $3.5 million (2011) to $3.75 million.