Road rehabilitation work continues

The City of Prince George 2011 Capital Road Rehabilitation Program will continue next week.

The City of Prince George 2011 Capital Road Rehabilitation Program will continue next week.

Projects:

Where - Ospika Boulevard north bound lanes between 5th and 15th Avenues

When - Asphalt milling June 20 with paving on June 24 (Paving is weather dependant)

Duration - 1 week

Length - 2.32 lane kilometers

Estimated Cost - $312,820

Where - Ospika Boulevard south bound lanes between Massey Drive and Ferry Avenue

When - Asphalt milling June 21 with paving on June 27 (Paving is weather dependent)

Duration - 1 week

Length - 2.53 lane kilometers

Estimated Cost - $334,530

Where - Domano Boulevard between Moriarty and Trent

When - Asphalt milling June 22 with paving on June 28t(Paving is weather dependent)

Duration - 1 week

Length - 2.53 lane kilometers

Estimated Cost - $334,530

Where - P.G. Pulpmill Road between the east city limit and 685m west

When - Asphalt milling June 23 with paving on June 29 and 30 (Paving is weather dependent)

Duration - 1 week

Length - 1.37 lane kilometers

Estimated Cost - $389,170

"In 2011, council has committed to a road rehabilitation record budget of $3.5 million, up about 2.9 per cent from last year, with 11 capital paving projects identified for improvement," said Mayor Dan Rogers. "In addition to the capital program, there is also the road repair budget that includes approximately a million dollars for patching as part of the asphalt maintenance program."

Additionally, in 2012, council has committed to increase the annual road rehabilitation budget of $3.5 million (2011) to $3.75 million.