Site C's financial mysteries

On December 14, 2017, Premier John Horgan, stood in front of a microphone with Energy Minister Michelle Mungall. The imminent decision regarding the fate of the Site C project was soon to be sealed during this press conference.

Months after having been crowned as the new premier, Horgan became an apologist for the third dam on the Peace. He stated what former premier Christy Clark had already made clear during her tenure, saying her objective was to get Site C "past the point of no return."

article continues below

This was, in effect, the identical statement made by Horgan during his December press conference. He also pointed out that it was too late to stop the project. As a result, the NDP could not and would not justify stopping the project.

In moving forward, Horgan did announce, however, a new Project Assurance Board, which, according to him, would "mandate delivering the project on time and on budget." BC Hydro had also revised the Site C budget up to $10.7 billion, from an estimate of $8.9 billion in 2014.

So, this would be the final figure. No more diddling with numbers. The NDP had put its proverbial foot down with BC Hydro and told it to live within its means.

Fast forward to July 2019, and along comes BC Hydro's latest quarterly report, based on January 2019 to March 2019. In the 55 pages or so of fun facts, BC Hydro was required to release a variety of updates on the Site C project to the BC Utilities Commission.

In this latest update, BC Hydro was required, by law, to give the commission a variety of budgetary data based on its own best estimates.

Pages 51 to 53 of the report identify 13 specific "material project risks."

These are risks that BC Hydro has clearly identified about the Site C project. There are even more risks not included in this quarterly report.

BC Hydro did not include risks that might affect certain partners or contractors under its "confidentiality obligations or solicitor-client privilege" clause.

With each description of identified risks comes the BC Hydro risk response. Here is the general list of risks and BC Hydro's responses:

River diversion delay - increased costs

Borrowing costs for project - interest costs above amount budgeted

Labour costs - increases beyond prescribed amounts

Safety incidents - associated costs

Work fronts other than left bank diversion - increased cost

Highway 29 realignment - overall cost increase

Spillway design changes - higher construction costs

Indigenous groups & issues - increased costs

Insufficient local aggregate - increased costs

Reservoir clearing - overall cost increases

Roller compacted concrete productivity - schedule not achieved

Hwy 29 realignment not completed on time - increased costs

Retention of skilled workers - productivity and cost

If each of the known 13 categories are going to cost more, and there are still those confidential additional risks, another question is: what is the real cost increase in dollars? Will it be more than the overall allotment already prescribed by Horgan and Mungall?

Given that BC Hydro has not given any definite numbers for the above increases in its report adds to the financial mystery.

The real litmus test will come from the Horgan government's response to the report. The likelihood of the general public learning of any specific amount increases referred to in the report also seems highly unlikely. We are rarely, if ever, given the appropriate numbers of cost overruns.

In November 2017, the BC Utilities Commission did its own study of Site C costs and overruns and identified a possible number as high as $12 billion for the Site C project.

If this is the case, the NDP might well be willing to "rationalize" its latest budget figure upwards to the $12 billion mark without any guilt or apprehension.

But Horgan's Project Assurance Board mandates that the project be delivered on budget. Horgan and Mungall may well be hoping that the public has simply forgotten about his promises through the Assurance Board.

Public be warned: Look forward to more excuses, finger pointing, whitewashes, and blame deferrals coming from the NDP and BC Hydro as costs continue to skyrocket upwards of $12 billion.

-- Mike Kroecher is an artist and retired resident of the Peace. Rick Koechl is a retired teacher of the Peace.

Read Related Topics

Comments

NOTE: To post a comment you must have an account with at least one of the following services: Disqus, Facebook, Twitter, Google+ You may then login using your account credentials for that service. If you do not already have an account you may register a new profile with Disqus by first clicking the "Post as" button and then the link: "Don't have one? Register a new profile".

The Prince George Citizen welcomes your opinions and comments. We do not allow personal attacks, offensive language or unsubstantiated allegations. We reserve the right to edit comments for length, style, legality and taste and reproduce them in print, electronic or otherwise. Comments that contain external links will not be permitted. For further information, please contact the editor or publisher, or see our Terms and Conditions.

comments powered by Disqus

Trudeau blackface POLL

Will the photos of Justin Trudeau in blackface influence how you vote in the election?

or  view results

Sign Up For Our e-Newsletter!
  • 97/16

    Prince George's Weekly News

Popular Citizen

Community Event Calendar


Find out what's happening in your community and submit your own local events.

Lowest Gas Prices in Prince George
Prince George Gas Prices provided by GasBuddy.com