Two more City paving projects are set to begin next week.
Starting Monday, a crew will begin work on 2.8 lane kilometres on Old Summit Lake Road between Hardy Road and Shady Valley Road. The work, estimated to cost $396,160, will take five days.
And on Tuesday, work will begin on 1.5 lane kilometres along Cranbrook Hill Road between Kueng Road and Foothills. The project is expected to take 10 days and cost $309,580.
Both projects are weather dependant.